Milestone Duration
Project Kickoff:
Documentation outlining process, milestone schedule and key responsibilities
0 Days 2/22
How the Game Will Work:
• How the game will look
• How to store data of music for the game
• Work on the graphics for the hulls
1 week 2/22- 3/1
Fine-Tune the Logistics of the Project:
• Continue working on the graphics
• Use Google and LITS to research copyrighted music and rules
• Meet with Audrey to talk over what classes are needed for the coding in the game
1 week 3/1-3/8
Data Storage and Classes Determination:
• Use Google to research song-data storage methods
• Set up classes to begin code and game design
• Work on graphics of the project
1 week 3/8-3/15
Begin Implementation of Game Design:
• Input classes to begin code and game design
4 weeks 3/15-4/12
Debug Game and Code:
• Test game to work out bugs and code
2 weeks, 4 days 4/12-4/30
Final Project Deadline:
3/4 days 4/30-5/3